Europort Shëngjin: 2013 business plan investment €2.2 billion and indicative 2026 indexation approximately €2.645 billion

 Europort Shëngjin : the 2013 business plan and an indicative cost comparison for 2026

 Europort Shëngjin  – Eagle of the Adriatic was developed as a proposed deep-sea port and logistics project for Albania and Southeast Europe. A comparison of its historical business plan with an informative annex dated 3 November 2026 helps explain the scale of the planned investment and the need for an updated assessment.

What the 2013 business plan states

The supplied business plan is Version III, dated 15 April 2013 and last updated on 12 October 2013. Page 27 sets out an investment of €2.2 billion, plus €200 million in construction-period interest, bringing total funding requirements to €2.4 billion.

These are historical planning figures. The document describes a preliminary financial outlook; its schedules, revenue projections and statements about future development must be read in their original historical context.

What the 2026 comparison shows

The informative annex applies a linked series of Albania’s INSTAT construction cost indices for dwellings as a proxy. It assumes Q4 2014 as the price baseline and uses Q2 2026 as the final reference period. This is a comparison with the investment recorded in the 2013 plan, not an index measured from 2013.

Basis Amount
Investment in the historical business plan €2.200 billion
Indicative indexation factor 1.20220848
Indicative indexed amount ≈ €2.645 billion
Arithmetic increase ≈ €444.86 million (+20.22%)

How these figures should be understood

Approximately €2.645 billion is a conditional indexation result, not a verified current project cost, an independent valuation or a compensation claim. The index concerns dwelling construction, rather than seaports. It does not separately price breakwaters, tunnels, dredging, cranes, imported equipment or changes in exchange rates. Applying one factor to all categories is illustrative.

The original €200 million of construction-period interest is excluded from the indexation. A current financing assessment would require a new model of timing, interest rates and capital structure. The comparison is not a quotation of market prices on the publication date.

A basis for further technical and financial review

The two documents serve different purposes: the business plan records historical planning, while the annex illustrates one possible index-based comparison. A reliable present-day estimate would require updated technical scope, quantities, specialist prices, environmental requirements and a financing model.

Documentary basis:  Europort Shëngjin  – Business Plan, Version III, updated 12 October 2013, page 27; informative cost-indexation annex dated 3 November 2026. The illustration depicts a project concept.

Full documents

Both documents are in English.

The business plan is published as a historical document. Its forecasts do not describe the current status of the project.